Jamshedpur, Aug. 5: The team of Kalinganagar Township Project (KTP) has achieved milestone of pouring 15000 Cum of concrete in the project on July 31, 2016.
The excavation work was started in F Block on January 20, 2016 while Batching Plant kicked off on February 11, 2016. The largest quantity of the project – Footing at E block – 532-cum got completed in July month, which has poured @ 20 Cum per Hour within 28 hrs.
The foundations have been completed in F#1, D & E blocks.
Senior leadership visits Kalinganagar
Andrew Page, vice-president, safety, India &SE Asia, Tata Steel, visited Kalinganagar Township Project site along with Rajiv Kumar, vice-president, operations, Kalinganar, and Bibhudutta Mohanty, chief, safety, KPO-Operations, Tata Steel on July 7, 2016.